Hamilton Community Energy - a Hamilton Utilities company
home contact HCE news links faqs careers
long-term goals
current projects
future opportunities
in the community

Energy Centre Progress:
week 4
week 8
week 12
week 24
week 36
special report

construction archive

HCE’s Energy Centre Week 8
Over the past four weeks progress continued with the distribution piping. The photo below was shown in the Week 4 Report and is being shown here again as a "before" and "after" look at the grounds leading to the entrance of Sir John A. It was important to have the grounds restored before students returned to school.

BEFORE

This piping will service Sir John A Macdonald School and was installed early to avoid the upcoming school year.

AFTER

Fortunately the large maple tree on the right survived the excavation. The contractor nurtured it along with burlap around the root ball and regular soakings during the extremely hot construction period. What this photo does not show is the contrast between the new sod we planted versus the dried out "hay" on the left. Again, thanks to our hot weather.

With most of the pile caps poured and set...

Crews begin constructing the forms for grade beams.

Tom Fehr, HCE's new Chief Engineer supervises the concrete pouring for the grade beams. Concrete quality is absolutely critical at this stage so each and every load is tested and if it does not meet specs it is rejected and sent away. An independent consulting firm, Trow Consulting, was hired to perform quality control testing throughout the construction process. On this particular day, two loads don't meet specifications and are refused.

Welding crews continue to form joint kits on the distribution piping. Now you know where the term "in the trenches" originated.

OOPS!

The contractor and HCE hit water. A water main is undermined and breaks, filling the trench and setting crews back a few days until the water can be removed and the pipe, which is at the bottom of this 10 foot trench, is cleaned and dried out!

A look at the back of City Hall before...

This.

When weather does not permit outside work to proceed, crews turn their attention to the kilometers of indoor pipe winding its way through basements and garages. Here an expansion loop is installed in the basement storage room of Jackson Square.

top | go to week 12

 

 
 

long-term goals | current projects | future opportunities | in the community  
home | contact us | news | links | faqs | careers | Privacy Policy

® Hamilton Community Energy is a registered trademark of Hamilton Utilities Corporation.

Hamilton Utilities Corporation